TVA uses sand baskets as temporary fixes for flawed flooding calculations
Sand baskets installed to protect against extreme flooding and protect nuclear plants at Watts Bar and three other TVA dams have upstream neighbors unhappy about their new views.
But the safety vs. beauty question — prompted by a decades-old mistaken calculation by TVA — may mean even more dams must be raised with sandbags or permanent fixes, according to the Tennessee Valley Authority and the Nuclear Regulatory Commission.
“We had to fix the problem by raising the embankments as soon as we could or possibly have to shut down [Watts Bar and Sequoyah nuclear] plants. That could result in $3 million to $5 million a day in lost generation,” said Mike Eiffe, TVA program manager for hydrology and hydraulics.
Compared to those numbers, TVA’s cost to prepare for what utility officials have called a “highly unlikely probable maximum flood” would seem to be chump change.
The project involved placing temporary cages of sand — most about 4 by 4 feet — atop the sides and embankments of the Watts Bar, Fort Loudoun, Tellico and Cherokee dams. The goal was to protect the dams and downstream plants from a flood about four times the amount of the region’s heaviest known rainfall.
The cost was $4.3 million, TVA spokesman Travis Brickey said.
TVA also is paying $2 million for a consultant to study whether similar fixes are needed at its 45 other dams, and it has a $400,000 environmental impact study under way to determine whether the first four dams need a more permanent fix, said Eiffe and Brickey.
“Its easy to think it [the probable maximum flood] will never happen here, but ‘never’ is a big word,” Brickey said. “A lot of people didn’t think the flooding of most of downtown Nashville would happen either, or that anyone would have to blow up dikes on the Mississippi. But those things did happen.”
What happened?
The concern didn’t begin with the nuclear meltdowns at Japan’s Fukushima Dai-ichi Nuclear Plant in March after a 9.0 earthquake and resulting tsunami.
And it wasn’t prompted by changing weather patterns or new rainfall forecasting models.
TVA and other nuclear operators have always had to design plants for what the NRC calls the probable maximum flood. And the size of that flood must have a site-specific estimation.
But when TVA began an effort to relicense the still-unfinished Bellefonte Nuclear Plant in northern Alabama, the utility couldn’t document how its original flood calculation was made. NRC ordered the estimate redone and slapped TVA with three violations in 2008.
Watts Bar Tennessee - News

A sign warns visitors to stay off of sand baskets that line the earthen dam portion of Watts Bar Dam near Spring City, Tenn. The baskets were designed as a prevention to flooding in a worse case disaster. A “probable maximum flood” is the

Tucked into the foothills of Eastern Tennessee, Watts Bar took 23 years to build, at a cost of nearly $8 billion. It was, Keteyian says, shut down in the mid-1980s over an avalanche of safety issues. In 1986, one independent report alone documented

Jimmy Matlock of Lenoir City said Wednesday he planned to contact other lawmakers who also have constituents affected by TVA's decision in 2009 to install the sand baskets — some of them 7 feet tall — at the Fort Loudon, Tellico, Cherokee and Watts
the Tennessee Valley Authority is considering removing or replacing the controversial flood barriers. In 2009 TVA installed "gambion" barriers — made of wire mesh filled with sand or dirt — on Fort Loudon, Tellico, Cherokee and Watts Bar dams to

Along with the possibility of restarting work at Bellefonte, in recent years we have upgraded our Browns Ferry 1 reactor, also in Alabama, and we are completing a second reactor at our Watts Bar plant, in eastern Tennessee.
Westinghouse to ship fuel to Watts Bar, TN reactor | PROS
June 21 (Reuters) - Westinghouse Electric Company said on Monday it will begin shipping nuclear fuel to the Tennessee Valley Authority's (TVA) Watts Bar Unit 2 reactor in Tennessee. Westinghouse will ship the fuel assemblies between late June and August, it said in a statement. Fuel loading is expected to begin in 2012 at Watts Bar 2, which is currently under construction, Westinghouse said. Last week, Tennessee Valley Authority (TVA) received a license from the Nuclear Regulatory Commission (NRC) authorizing the receipt of fresh nuclear fuel for eventual use in its proposed Unit 2 reactor. [ID:nSGE75E011] Once licensed to operate by the NRC, Unit 2 will be the will add 1,180 megawatts to the TVA power system, Westinghouse said. Pittsburg-based Westinghouse is majority owned by Toshiba Corp (6502.T) and Shaw Group (SHAW.N).
-----------------------------------------------------------
PLANT BACKGROUND/TIMELINE
STATE: Tennessee
COUNTY: Rhea
TOWN: Spring City
OPERATOR: TVA
OWNER(S): TVA
UNIT(S): 1 - 1,123 MW Westinghouse pressurized water reactor
FUEL: Nuclear
DISPATCH: Baseload
TIMELINE:
1973 - Plant construction starts
1988 - Unit 2 construction stopped when it was about 80 percent complete. TVA said it stopped construction due to a reduction in demand for power. Anti-nuclear activists however hailed the work stoppage as a victory
1966 - Unit 1 enters commercial service - last nuclear power reactor to enter service in the U.S.
2007 - TVA Board approved the completion of the 1,180 MW Unit 2 at an estimated cost of $2.5 billion.
Watts Bar Tennessee - Bookshelf
Tennessee's New Deal landscape, a guidebook
RHEA COUNTY Watts Bar Dam and Lake (1939-42), Tennessee Highway 68, Spring City vicinity Watts Bar is the best TVA property in Tennessee to witness the ...Fire at Watts Bar Hydroelectric Plant; Rhea County, Tennessee
BUILDING STrUCTUrE AND SITE The Watts Bar Hydroelectric Plant is located at mile marker 529.9 of the Tennessee River, sitting halfway between Knoxville and ...The compleat Tennessee angler, everything you need to know about fishing in the Volunteer State
CHAPTER 18 Watts Bar Lake The Lake that Has Everything Watts Bar Lake draws a lot of attention from ... Watts Bar has an advantage over many East Tennessee ...Paddling the Tennessee River, a voyage on easy water
... 7S>az / J istening to our bright yellow transistor radio, Jasper and f I passed below the twin bridges at the town of Loudon, ^^m>s on Watts Bar Lake. ...Journal of the Tennessee Academy of Science
Zinc analyses were conducted at the University of Tennessee using an Instrumentation ... Looking at Cherokee, Norris, and Watts Bar reservoirs during the ...Casual Posts Directory
Watts Bar Lake, Tennessee, US - Community and Visitors Guide
Examine a guide to recreational opportunities, rentals, real estate listings, hotels and cultural events in the water district of Watts Bar Lake.
Watts Bar Dam - Wikipedia, the free encyclopedia
Watts Bar Dam is a hydroelectric dam on the Tennessee River in Meigs ... Watts Bar Dam is located approximately 530 miles (850 km) upstream from the mouth of the ...
TVA: Watts Bar Reservoir
The overall ecological health condition for Watts Bar Reservoir rated poor in 2010. ... Watts Bar Reservoir is located on the Tennessee River below Knoxville in east Tennessee. ...
Watts Bar Nuclear Generating Station - Wikipedia, the free ...
Watts Bar Nuclear Power Plant Units 1 & 2 cooling towers and containment ... Watts Bar supplies enough electricity for about 750,000 households in the Tennessee Valley. ...
TVA: Watts Bar Nuclear Plant
Watts Bar Nuclear Plant. Watts Bar Nuclear Plant is located just south of Watts Bar Reservoir on the Tennessee River near Spring City in east Tennessee. ...